QUANTITY ESTIMATING
 

   
Surface Course: 50mm pavers
Bedding Course: 20mm of compacted coarse washed sand
Base Course: 100mm of A-Grade 20mm fine crushed rock
 
bulletPAVERS
bullet38 pavers per m².  Allow 40 pavers per m² for any cutting necessary on site at the time of ordering.
bulletSAND
bullet25mm uncompacted sand per m² = 1m³ of sand for every 40m² of paving OR
.025m³ of sand per
m
² of paving.
bulletBEDDING
bullet100mm of compacted rock per m² = 1m³ of roadbase for every 10m² of paving OR
.1m³ of roadbase  per
m
² of paving.

(Note:  2 ton of loose roadbase is approximately equal to 1 compacted cubic metre).

Example:  A 60m² driveway
bullet 
Pavers 60m² x 40 pavers per m² = 2400 pavers
bullet 
Sand 60m² x .025 sand per m³ = 1.5m³ bedding sand
bullet 
Roadbase 60m² x .1 compacted rock = 6m³ rock (12 loose tons)

 

Home / Products / Online Assistance / Photo Album / About Heritage / Suppliers / Credit Application

 

 
Back to Basics
Theory Into Practice
Quantity Estimating
Print Version

     Copyright ©2002, 2003 Heritage Building Products.  All rights reserved.

 


Web Development
Website Concepts.
This page was last updated 04 February, 2010